Roads23BH0183

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ECHAGUE - DINAPIGUE ALTERNATE ROUTE, PACKAGE 1, ECHAGUE, ISABELA

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ECHAGUE - DINAPIGUE ALTERNATE ROUTE, PACKAGE 1, ECHAGUE, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱40,712,641.15. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MA TESORO CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gumbaun-San Isidro Flood Control Project, Echague - San Isidro, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

83 projects · ₱1.8B total · 1 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0361+590 - K0361+844, K0361+866 - K0364+014

Region II, Region II

2025₱134.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF GAGABUTAN FLOOD CONTROL STRUCTURE STA. 0+620 - STA. 1

Isabela 4th DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS - MAHARLIKA HIGHWAY - K0346+694 - K0347+282, K0347+430 -K0347+993, K0350+700 - K0351+561, K0352+0

Region II, Region II

2025₱72.5M
Past target date (DPWH On-Going)
No sat.

Construction of Amobocan, Flood Control Project, Amobocan, Cauayan, Isabela (Package 1)

CITY OF CAUAYAN (ISABELA), ISABELA, Region II

2024₱70.8M
Reported complete (DPWH)
No sat.

Construction of Carabatan Chica Flood Control Project, Cauayan City, Isabela

CITY OF CAUAYAN (ISABELA), ISABELA, Region II

2024₱70.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAYOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BARINGIN NORTE FLOOD CONTROL

Isabela 4th DEO, Region II

2024₱70.8M
Reported complete (DPWH)
View all 83 projects →

4. Implementation

Contract Amount

₱40,712,641.15

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 22, 2023

Target End

January 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.