Bridges23FO0076

CLUSTER XIII-2023: 1.) BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF HANGING BRIDGE AND APPROACHES AT MT. MASARAGA, BRGY. AMTIC, LIGAO CITY; 2.) BIP-ACCESS ROADS AND/OR BRID

CLUSTER XIII-2023: 1.) BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF HANGING BRIDGE AND APPROACHES AT MT. MASARAGA, BRGY. AMTIC, LIGAO CITY; 2.) BIP-ACCESS ROADS AND/OR BRID is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱9,620,000.00. Status: Reported complete (DPWH). Contractor on record: JUDERO BUILDERS AND SUPPLY. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Possible match · 76%

INFRA-PB-2022-007

₱6,496,910.30 · JUDERO BUILDERS AND SUPPLY

Contractor

C

7 projects · ₱40.1M total · 0 flags

Other projects by this contractor

View all 7 projects →

4. Implementation

Contract Amount

₱9,620,000.00

Progress

Reported complete (DPWH)

Start Date

July 17, 2023

Target End

March 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.