Roads21GN0060

CONCRETING OF ROAD, BRGY. CULO, PULUPANDAN, NEGROS OCCIDENTAL

CONCRETING OF ROAD, BRGY. CULO, PULUPANDAN, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱19,007,995.60. Status: Reported complete (DPWH). Contractor on record: EZ GOLD CONST. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱1,400

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱19,007,996 · EZ GOLD CONSTRUCTION AND SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-12-29 → 2025-08-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF ROAD, BRGY. CULO, PULUPANDAN, NEGROS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱1,400,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Camansi River, Brgy. Zamora, Pontevedra, Negros Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Occidental 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21GN0060 - Concreting of Road, Brgy. Culo, Pulupan

₱19,007,995.60 · EZ GOLD CONSTRUCTION AND SUPPLY

Award / contract ref: CONTRACT ID NO. 21GN0060

4. Implementation

Contract Amount

₱19,007,995.60

Progress

Reported complete (DPWH)

Start Date

March 22, 2021

Target End

July 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “CONCRETING OF ROAD, BRGY. CULO, PULUPANDAN, NEGROS OCCIDENTAL.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/664e513d-0653-4f4b-89c2-f37711a768c9

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros OccidentalPulupandanCulo
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.