GAA 2025 OO-125DM0011

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CATANAUAN DIVERSION ROAD, QUEZON (PACKAGE 6), QUEZON, CATANAUAN, QUEZON

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CATANAUAN DIVERSION ROAD, QUEZON (PACKAGE 6), QUEZON, CATANAUAN, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱94,560,378.70. Status: Past target date (DPWH On-Going). Contractor on record: R T Y CONST. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation, Structure along Bingabing Creek, Brgy. Madulao, Catanauan, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

177 projects · ₱6.4B total · 0 flags

Other projects by this contractor

No sat.

MFO-1 NATIONAL ROAD NETWORK SERVICES NETWORK DEVELOPMENT CONSTRUCTION OF BY-PASSES/DIVERSION ROADS INCL. ROW LOPEZ BY-PASS ROAD, INCL. ROW, QUEZON

Region IV-A, Region IV-A

2017₱145.9M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (CONCRETE PAVING) ALONG SAN FRANCISCO-SAN ANDRES-SAN NARCISO ROAD, K0318+216-K0321+966

Quezon 3rd DEO, Region IV-A

2016₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0272+067-K0275+840, BUENAVISTA, QUEZON

Region IV-A, Region IV-A

2017₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0262+323-K0266+025, BUENAVISTA, QUEZON

Region IV-A, Region IV-A

2017₱144.7M
Reported complete (DPWH)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM, ROAD WIDENING/PRIMARY ROADS, DAANG MAHARLIKA (LZ) K0192+100.00-K0192+729.00, K0201+730-K0203+839.00, QUEZON

Region IV-A, Region IV-A

2018₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG MSR JCT-LOPEZ-CATANAUAN ROAD, K0248+912-K0250+790 & K0250+816-K0254+275, CATANAUAN, QUEZON

Region IV-A, Region IV-A

2017₱144.3M
Reported complete (DPWH)
View all 177 projects →

4. Implementation

Contract Amount

₱94,560,378.70

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2025

Target End

December 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.