Bridges19PF0024

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TABA-AO BRIDGE (B00913LZ) ALONG ACOP-KAPANGAN-KIBUNGAN-BAKUN ROAD

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TABA-AO BRIDGE (B00913LZ) ALONG ACOP-KAPANGAN-KIBUNGAN-BAKUN ROAD is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱994,191.12. Status: Reported complete (DPWH). Contractor on record: SISSI-IT CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

6 projects · ₱43.1M total · 0 flags

4. Implementation

Contract Amount

₱994,191.12

Progress

Reported complete (DPWH)

Start Date

July 10, 2019

Target End

October 8, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.