GAA 2025 SSP25I00137

SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD, BARANGAY BATIAWAN - BARANGAY PANGABUTAN, TAFT, EASTERN SAMAR

SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD, BARANGAY BATIAWAN - BARANGAY PANGABUTAN, TAFT, EASTERN SAMAR is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱28,939,913.86. Status: Past target date (DPWH On-Going). Contractor on record: CHRIZMARIE BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱28,939,914 · CHRIZMARIE BUILDERS AND CONSTRUCTION SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    40% reported · imagery 2019-09-17 → 2025-06-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD, BARANGAY BATIAWAN - BARANGAY PANGABUTAN, TAFT, EASTERN SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CID No. 25I00137

₱28,939,913.86 · CHRIZMARIE BUILDERS AND CONSTRUCTION SUPPLY

Contractor

C

71 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 15: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BASEY - MAYDOLONG, EASTERN SAMAR; 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LE

Region VIII, Region VIII

2023₱247.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO KALAWIT - BARANGAY CADIAN, ORAS, EATERN SAMAR

Region VIII, Region VIII

2024₱168.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF MAYDOLONG - BASEY ROAD, EASTERN SAMAR

Region VIII, Region VIII

2025₱158.1M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS JCT. BUENAVISTA - LAWAAN - MARABUT RD (S00147SM), K0954+622 - K0955+000, K0955+700 - K0957+600, K0959+594 - K0960+624

Eastern Samar DEO, Region VIII

2025₱133.7M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. LUMATOD - DANAO, TAFT, EASTERN SAMAR

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. POLANGI - GAYAM, TAFT, EASTERN SAMAR LD

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
View all 71 projects →

4. Implementation

Contract Amount

₱28,939,913.86

Progress

Past target date (DPWH On-Going)

Start Date

April 10, 2025

Target End

September 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)Eastern SamarTaftPangabutan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.