Buildings and Facilities22BK0107

BASIC INFRASTRUCTURE PROGRAM (BIP) EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EVACUATION CENTER DUMABATO NORTE, MADDELA, QUIRINO

BASIC INFRASTRUCTURE PROGRAM (BIP) EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EVACUATION CENTER DUMABATO NORTE, MADDELA, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,937,866.37. Status: Reported complete (DPWH). Contractor on record: JIT BUILDERS. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

15 projects · ₱80.1M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - NRJ VILLA SUR - SAN PEDRO - CABUA-AN - YSMAEL - DISIMUNGAL RD - K0368+508 - K0368+766, K0368+1087 - K0369+246, MADD

Quirino DEO, Region II

2024₱15.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF GABRIELA SILANG ROAD, BARANGAY GABRIELA SILANG, DIFFUN, QUIRINO

Quirino DEO, Region II

2023₱9.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY GABRIELA SILANG, DIFFUN, QUIRINO

Quirino DEO, Region II

2023₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION) MAGSAYSAY NATIONAL HIGH SCHOOL, DIFFUN, QUIRINO

Quirino DEO, Region II

2022₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ALICIA ROAD, BARANGAY ALICIA, AGLIPAY, QUIRINO

Quirino DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGA/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY DIBIBI, CABARROGUIS, QUIRINO

Quirino DEO, Region II

2023₱4.9M
Reported complete (DPWH)
View all 15 projects →

4. Implementation

Contract Amount

₱2,937,866.37

Progress

Reported complete (DPWH)

Start Date

April 1, 2022

Target End

September 22, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.