Bridges17BB0014

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NAT'L RD-REHAB./MAJOR REPAIR OF PERMANENT BRIDGES-BARACAOIT BRIDGE (B02074LZ) ALONG JGCCSMBPR, GATTARAN, CAGAYAN 1ST LD

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NAT'L RD-REHAB./MAJOR REPAIR OF PERMANENT BRIDGES-BARACAOIT BRIDGE (B02074LZ) ALONG JGCCSMBPR, GATTARAN, CAGAYAN 1ST LD is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱15,934,974.28. Status: Reported complete (DPWH). Contractor on record: TRIBU DESIGN. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Chico River, Piat, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0011469

₱5,880,000.00 · FY2017

Released to PENRO Zamboanga Modifi del Norte Expens develo Zamboa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

45 projects · ₱604.4M total · 0 flags

Other projects by this contractor

View all 45 projects →

4. Implementation

Contract Amount

₱15,934,974.28

Progress

Reported complete (DPWH)

Start Date

August 2, 2017

Target End

November 22, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.