Roads21DE0045

LOCAL INFRASTRUCTURE PROGRAM - CONCRETING OF ROAD, BARANGAY CUMBA, BATANGAS CITY, BATANGAS

LOCAL INFRASTRUCTURE PROGRAM - CONCRETING OF ROAD, BARANGAY CUMBA, BATANGAS CITY, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱2,970,000.00. Status: Reported complete (DPWH). Contractor on record: R M TEJADA CONST AND SUPPLIES CORP. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Sampaga River, Sitio Kanluran, Barangay Dumuclay , Batangas City, Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Batangas 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

33 projects · ₱371.9M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING (LIVING QUARTERS) OF PHILIPPINE COAST GUARD SOUTHERN TAGALOG BRG

Batangas 2nd DEO, Region IV-A

2025₱33.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, SITIO CUMBA, BRGY. SAN JOS

Batangas 2nd DEO, Region IV-A

2024₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BRGY. SULPOC, TANAUAN, BATANGAS (PACKAGE B)

Batangas 3rd DEO, Region IV-A

2023₱29.7M
Reported complete (DPWH)
No sat.

CY 2019 BASIC EDUCATIONAL FACILITIES FUND - CONSTRUCTION OF 2STY 6CL AT CALO ELEMENTARY SCHOOL, LOBO, BATANGAS

Batangas 2nd DEO, Region IV-A

2019₱21.3M
Reported complete (DPWH)
No sat.

CY 2019 BASIC EDUCATIONAL FACILITIES FUND - CONSTRUCTION OF 2STY 6CL AT APAR ELEMENTARY SCHOOL, LOBO, BATANGAS

Batangas 2nd DEO, Region IV-A

2019₱21.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, BATANGAS-LOBO RD - K0119 + 800 - K0120 + 469

Batangas 4th DEO, Region IV-A

2024₱21.0M
Reported complete (DPWH)
View all 33 projects →

4. Implementation

Contract Amount

₱2,970,000.00

Progress

Reported complete (DPWH)

Start Date

February 3, 2021

Target End

March 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.