Trust Funds 202121LH0160

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. CATIGAN, TORIL DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) CONSTRUCTION OF WATER SUPPLY SYSTEM AT PUROKS 1, 2, 3, 4, 6, 7, 8, 9 AND 11, BRGY. CATIGAN, DAVAO CITY (2) CONSTRUCTION OF ROAD AT PUROK 5, 9 AND 10,

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. CATIGAN, TORIL DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) CONSTRUCTION OF WATER SUPPLY SYSTEM AT PUROKS 1, 2, 3, 4, 6, 7, 8, 9 AND 11, BRGY. CATIGAN, DAVAO CITY (2) CONSTRUCTION OF ROAD AT PUROK 5, 9 AND 10, is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱15,609,525.72. Status: Reported complete (DPWH). Contractor on record: ZJN DEVELOPMENT CONST. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Mitigation Structure protecting Daang Maharlika (MN) at Brgy. Bunawan, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao City 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱15,609,525.72

Progress

Reported complete (DPWH)

Start Date

September 20, 2022

Target End

February 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.