GAA 2025 SSP25FL0073

CONST OF MP BUILDING (COVERED COURT) AT BRGY. HIDHID, BRGY. LABOY, MATNOG, BRGY. JAMORAWON, BRGY. LA

CONST OF MP BUILDING (COVERED COURT) AT BRGY. HIDHID, BRGY. LABOY, MATNOG, BRGY. JAMORAWON, BRGY. LA is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱48,510,000.00. Status: Past target date (DPWH On-Going). Contractor on record: ALHADRAX CONST AND SUPPLY. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Capuy, Sorsogon City, Sorsogon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Sorsogon 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25FL0073-Construction of Multi-Purpose Building (C

₱48,510,000.00 · ALHADRAX CONSTRUCTION AND SUPPLY

Contractor

92 projects · ₱1.9B total · 0 flags

Other projects by this contractor

View all 92 projects →

4. Implementation

Contract Amount

₱48,510,000.00

Progress

Past target date (DPWH On-Going)

Start Date

July 25, 2025

Target End

December 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.