Buildings and Facilities20NB0047

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STA. MARIA, PROSPERIDAD, AGUSAN DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STA. MARIA, PROSPERIDAD, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱4,872,930.87. Status: Reported complete (DPWH). Contractor on record: ABADA CONST AND SUPPLY. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control structures along Riverbank of Maug Bridge Phase II (Upstream), Prosperidad, Agusan del Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Agusan del Sur 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

81 projects · ₱387.5M total · 0 flags

Other projects by this contractor

View all 81 projects →

4. Implementation

Contract Amount

₱4,872,930.87

Progress

Reported complete (DPWH)

Start Date

November 22, 2020

Target End

March 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.