Buildings and Facilities17BK0145

CONSTRUCTION OF ONE-STOREY THREE CLASSROOM SCHOOL BUILDING IFUGAO VILLAGE INTEGRATED SCHOOL, DIFFUN, QUIRINO

CONSTRUCTION OF ONE-STOREY THREE CLASSROOM SCHOOL BUILDING IFUGAO VILLAGE INTEGRATED SCHOOL, DIFFUN, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱3,780,502.44. Status: Reported complete (DPWH). Contractor on record: NC CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

93 projects · ₱372.3M total · 0 flags

4. Implementation

Contract Amount

₱3,780,502.44

Progress

Reported complete (DPWH)

Start Date

November 10, 2017

Target End

February 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.