Roads23B00017

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 2, CAGAYAN

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 2, CAGAYAN is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱106,149,831.09. Status: Past target date (DPWH On-Going). Contractor on record: JC PALOMO CONST & CONST SUPPLY. Figures trace to dpwh.

Region II, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

15 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (LZ) - K0249 + 000 - K0251 + 000, K0284 + 542.70 -

Region II, Region II

2024₱181.3M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NAT'L ROAD SYSTEM: NETWORK DEV'T: ROAD WIDENING-PRIMARY ROADS ALONG DAANG MAHARLIKA (LZ), K0309+000-K0309+467, K0314+000-K0314+208, K0317+000-K0317+245, K0335+000-K0336+000, CORDON, SAN ISIDRO, ECHAGUE, ISABELA

Region II, Region II

2018₱166.9M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - RAMON-CORDON-DIADI BYPASS ROAD, DIADI, NUEVA VIZCAYA

Region II, Region II

2024₱101.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BAYOMBONG-QUEZON-BAGABAG ROAD, NUEVA VIZCAYA

Region II, Region II

2024₱95.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BAYOMBONG - QUEZON - BAGABAG ROAD, NUEVA VIZCAYA

Region II, Region II

2025₱52.8M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱49.4M
Past target date (DPWH On-Going)
View all 15 projects →

4. Implementation

Contract Amount

₱106,149,831.09

Progress

Past target date (DPWH On-Going)

Start Date

April 20, 2023

Target End

April 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.