Roads24CB0021

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD FROM ROMAN EXPRESSWAY LEADING TO DUHAT TRAIL AND VIEW DECK, BRGY. GEN. LIM, ORION, BATAAN

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD FROM ROMAN EXPRESSWAY LEADING TO DUHAT TRAIL AND VIEW DECK, BRGY. GEN. LIM, ORION, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱75,324,142.54. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LUCK-WELL CONST DEV'T CORP FORMERLY: LUCKWELL CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Calungusan River, Orion, Bataan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bataan 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

27 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BR. FR. THE NAT'L. RDS./S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ACCESS RD, BRGY. QUINAWAN, BAGAC TO BRGY. BIAAN, MARIVELES, BA

Region III, Region III

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD (PHASE I), BARANGAY QUINAWAN, BAGAC, BATAAN

Region III, Region III

2021₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRIDGES FR. THE NAT'L. RD./S LEAD. TO MAJ./STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ACCESS ROADS BRGY. QUINAWAN, BAGAC TO BRGY. BIAAN, MARI

Region III, Region III

2024₱189.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SEAPORT, BALANGONAN, JOSE ABAD SANTOS, DAVAO OCCIDENTAL

Davao Occidental DEO, Region XI

2019₱144.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS & BRIDGES-LOCAL ROADS-CONSTRUCTION OF ACCESS ROAD (PHASE I), BARANGAY QUINAWAN, BAGAC, BATAAN

Region III, Region III

2021₱144.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, UMAGOL RIVER, UPSTREAM, SEGMENT VR-2, BAGAC, BATAAN

Bataan 3rd DEO, Region III

2025₱118.2M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱75,324,142.54

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 6, 2024

Target End

October 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.