CONSTRUCTION OF BYPASSES/ DIVERSION ROADS INCLUDING ROW AT JCT. NATIONAL HIGHWAY R.T. LIM-JCT. NATIONAL HIGHWAY SIOCON ROAD (SURABAY-SAN FERNANDINO), ZAMBOANGA SIBUGAY 2ND DEO, BEG. OF PROJECT: K1827+600.00, END OF PROJECT: K1835+800.00, NET LENGTH: 8,200
CONSTRUCTION OF BYPASSES/DIVERSION ROADS INCLUDING ROW AT JCT. NATIONAL HIGHWAY R.T. LIM-JCT. NATIONAL HIGHWAY SIOCON ROAD (SURABAY-SAN FERNANDINO), ZAMBOANGA SIBUGAY 2ND DEO, BEG. OF PROJECT: K1827+600.00, END OF PROJECT: K1835+800.00, NET LENGTH: 8,200 is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱239,360,997.22. Status: Reported complete (DPWH). Contractor on record: 2M CONST & ENT. Figures trace to dpwh.
Total Contract Cost