Water Provision and Storage24IH0096

CONSTRUCTION OF WATER SYSTEM, CATARMAN, NORTHERN SAMAR (PHASE II)

CONSTRUCTION OF WATER SYSTEM, CATARMAN, NORTHERN SAMAR (PHASE II) is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱9,894,791.20. Status: Past target date (DPWH On-Going). Contractor on record: SMU CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Rawis, Laoang, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Northern Samar 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

43 projects · ₱729.4M total · 0 flags

4. Implementation

Contract Amount

₱9,894,791.20

Progress

Past target date (DPWH On-Going)

Start Date

September 26, 2024

Target End

March 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.