Bridges18G00075

CONSTRUCTION OF NAPTI BRIDGE ALONG NAPTI - MANDONG ROAD, NAPTI, BATAN, AKLAN

CONSTRUCTION OF NAPTI BRIDGE ALONG NAPTI - MANDONG ROAD, NAPTI, BATAN, AKLAN is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱111,681,040.75. Status: Reported complete (DPWH). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱111,681,040.75

Progress

Reported complete (DPWH)

Start Date

June 4, 2018

Target End

June 7, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.