Roads23I00089

INSTALLATION OF SOLAR STREETLIGHTS ALONG JCT. - TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD - K0917+073 - K0928+813 (S00167SM), EASTERN SAMAR

INSTALLATION OF SOLAR STREETLIGHTS ALONG JCT. - TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD - K0917+073 - K0928+813 (S00167SM), EASTERN SAMAR is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱96,398,192.28. Status: Reported complete (DPWH). Contractor on record: EC SOLICON BUILDERS. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

108 projects · ₱3.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PHASE II), VIGA, ANTEQUERA, BOHOL

Region VII, Region VII

2025₱101.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF SOLAR LED LIGHTINGS ON ROADS LEADING TO NEW BOHOL - PANGLAO INTERNATIONAL AIRPORT - PANGLAO ISLAND CIRCUMFERENTIAL ROAD (VIA

Region VII, Region VII

2022₱98.0M
Reported complete (DPWH)
No sat.

INSTALLATION OF SOLAR STREETLIGHTS ALONG BORONGAN - GUIUAN ROAD - K1037+000 - K1049+000 (S00171SM), EASTERN SAMAR

Region VIII, Region VIII

2023₱96.4M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES/STREETLIGHTS AND INTERNALLY ILLUMINATED (SOLAR) PAVEMENT MARKERS ALONG BDRY. SO. LEYTE - MAASIN - MACROHON - DAANG MAHARLIKA (S00194LT) - K1132+

Region VIII, Region VIII

2023₱96.4M
Reported complete (DPWH)
No sat.

INSTALLATION OF SOLAR STREETLIGHTS ALONG BORONGAN - GUIUAN RD. - K0924+(-403) - K0934+394, EASTERN SAMAR

Region VIII, Region VIII

2023₱96.4M
Reported complete (DPWH)
No sat.

INSTALLATION OF SOLAR STREETLIGHTS ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD - K0928+813 - K0939+948 (S00167SM), EASTERN SAMAR

Region VIII, Region VIII

2023₱96.3M
Reported complete (DPWH)
View all 108 projects →

4. Implementation

Contract Amount

₱96,398,192.28

Progress

Reported complete (DPWH)

Start Date

June 6, 2023

Target End

November 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.