Construction of Drainage Structure23DE0067

Construction of Calumpang East Line Canal, San Luis, Batangas

Construction of Calumpang East Line Canal, San Luis, Batangas is a DPWH-tracked public work in SAN LUIS (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱3,860,000.00. Status: Reported complete (DPWH). Contractor on record: SUPPLICON BUILDERS. Figures trace to sumbong.

SAN LUIS (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Isidro (Section 1), Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

65 projects · ₱280.8M total · 0 flags

4. Implementation

Contract Amount

₱3,860,000.00

Progress

Reported complete (DPWH)

Start Date

April 3, 2023

Target End

June 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.