Roads22MI0113

CONSTRUCTION OF FARM-TO-MILL ROAD, NATUTUNGAN ROAD 12, NATUTUNGAN, MATALAM, NORTH COTABATO

CONSTRUCTION OF FARM-TO-MILL ROAD, NATUTUNGAN ROAD 12, NATUTUNGAN, MATALAM, NORTH COTABATO is a DPWH-tracked public work in Cotabato 3rd DEO, Region XII. Reported contract value: ₱10,765,987.60. Status: Reported complete (DPWH). Contractor on record: LTB BUILDERS. Figures trace to dpwh.

Cotabato 3rd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment, Kabacan River Flood Control (Sta. 29+286 - Sta. 29+671 right bank, Matalam, Cotabato
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cotabato 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,765,987.60

Progress

Reported complete (DPWH)

Start Date

December 23, 2022

Target End

March 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.