Roads19FK0018

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROAD SORSOGON CITY COASTAL BY-PASS ROAD, PACKAGE 3, SORSOGON CITY

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROAD SORSOGON CITY COASTAL BY-PASS ROAD, PACKAGE 3, SORSOGON CITY is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱93,759,867.40. Status: Reported complete (DPWH). Contractor on record: A G ARAJA CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱93,759,867.40

Progress

Reported complete (DPWH)

Start Date

July 12, 2019

Target End

February 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.