Buildings and Facilities18CD0308

CONSTRUCTION OF SAN JOSE DEL MONTE CONVENTION CENTER (PHASE II), SAN JOSE DEL MONTE CITY, BULACAN

CONSTRUCTION OF SAN JOSE DEL MONTE CONVENTION CENTER (PHASE II), SAN JOSE DEL MONTE CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱137,435,470.62. Status: Reported complete (DPWH). Contractor on record: GRANDCONST BUILDERS CORP. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱137,435,470.62

Progress

Reported complete (DPWH)

Start Date

August 16, 2018

Target End

August 10, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.