Roads15GK0186No coordinates published by DPWH

REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE, CONSTRUCTION OF SLOPE PROTECTION ALONG JCT. NAT'L. RD. SAGAY-BATO-DIAN-AY-MARCELO-BALEA JCT. RD., CALATRAVA SECTION K0117+200-K0117+275, CALATRAVA, NEGROS OCCIDENTAL

REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE, CONSTRUCTION OF SLOPE PROTECTION ALONG JCT. NAT'L. RD. SAGAY-BATO-DIAN-AY-MARCELO-BALEA JCT. RD., CALATRAVA SECTION K0117+200-K0117+275, CALATRAVA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 1st DEO, Negros Island Region. Reported contract value: ₱7,437,453.89. Status: Reported complete (DPWH). Contractor on record: JAIME B CHING ENT. Figures trace to dpwh.

Negros Occidental 1st DEO, Negros Island Region

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Negros Island Region

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-C-16-0015251 · · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 15GK0186 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE, CONSTRUCTION OF SLOPE PROTECTION ALONG JCT. NAT'L. RD. SAGAY-BATO-DIAN-AY-MARCELO-BALEA JCT. RD., CALATRAVA SECTION K0117+200-K0117+275, CALATRAVA, NEGROS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Imbang River (both stream), Silay City, Negros Occidental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-16-0015251

₱-134,095.00 · FY2016

Released to Regional Office - X (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

400 projects · ₱12.8B total · 44 flags

4. Implementation

Contract Amount

₱7,437,453.89

Progress

Reported complete (DPWH)

Start Date

March 3, 2016

Target End

August 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE, CONSTRUCTION OF SLOPE PROTECTION ALONG JCT. NAT'L. RD. SAGAY-BATO-DIAN-AY-MARCELO-BALEA JCT. RD., CALATRAVA SECTION K0117+200-K0117+275, CALATRAVA, NEGROS OCCIDENTAL.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/821a933f-819e-42c0-b208-fbb1024beda7

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros Occidental
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.