GAA 2023 OO-123BA0040

ORGANIZATION OUTCOME 1: ENSURE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS; SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD, SABTANG, BATANES - PACKAGE 2

ORGANIZATION OUTCOME 1: ENSURE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS; SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA-NAKANMUAN ROAD, SABTANG, BATANES - PACKAGE 2 is a DPWH-tracked public work in Batanes DEO, Region II. Reported contract value: ₱39,778,332.42. Status: Reported complete (DPWH). Contractor on record: J H R ENT. Figures trace to dpwh.

Batanes DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Uyugan Flood Control (Valugan Section), Uyugan, Batanes
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batanes DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱39,778,332.42

Progress

Reported complete (DPWH)

Start Date

April 26, 2023

Target End

July 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.