Roads22KE0043

CONSTRUCTION OF SLOPE PROTECTION ALONG CAMIGUIN CIRCUMFERENTIAL ROAD BENONI SECTION 1 (NEAR BENONI ES),MAHINOG,CAMIGUIN

CONSTRUCTION OF SLOPE PROTECTION ALONG CAMIGUIN CIRCUMFERENTIAL ROAD BENONI SECTION 1 (NEAR BENONI ES),MAHINOG,CAMIGUIN is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱95,341,692.54. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 74%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Mapanag River, Sag±ay, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camiguin DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONSTRUCTION OF SLOPE PROTECTION ALONG CAMIGUIN CI

₱86,674,268.86 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT .

Contractor

Other projects by this contractor

No sat.

PROPOSED CONSTRUCTION OF THE COURT OF TAX APPEALS (CTA) BUILDING III - 6 STOREY BUILDING WITH 1 LEVEL BASEMENT AND ROOF DECK

National Capital Region, National Capital Region

2022₱328.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 2), ORION, BAT.

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPL. SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES, CONST. OF ROAD, BRGY. ALAS-ASIN IPAG (PHASE 2), MARIVE

Region III, Region III

2024₱304.2M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS- MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA-ABRA DE ILOG), PACKAGE C, OCCIDENTAL MINDORO

Region IV-B, Region IV-B

2023₱268.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (SAN NICOLAS SECTION), ILOCOS NORTE

Region I, Region I

2022₱260.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATUION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD, K0095+000-K0112+669 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 545 projects →

4. Implementation

Contract Amount

₱95,341,692.54

Progress

Reported complete (DPWH)

Start Date

June 29, 2022

Target End

April 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.