Roads21PG0007

CONSTRUCTION OF BARANGAY CABA TO BARANGAY BANGA ROAD, CABA, LAGAWE, IFUGAO

CONSTRUCTION OF BARANGAY CABA TO BARANGAY BANGA ROAD, CABA, LAGAWE, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,851,000.00. Status: Reported complete (DPWH). Contractor on record: DIAMOND J BUILDERS. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱7,260,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Boliwong Flood Control, Lagawe, Ifugao
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Ifugao 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

45 projects · ₱328.8M total · 0 flags

Other projects by this contractor

No sat.

REHAB./RECONST'N. OF NAT'L RDS. W/SLIPS,SLOPE COLLAPSE AND LANDSLIDE ALONG BAN-HUNG-BENGUET BDRY. RD.-K0358+674-K0358+704,K0375+190-K0375240,K0381+702-K0381+717,K0383+010-K0383+100,K0386+492,K0391+125-K0391+249,K0392+609-K0392+650,K0392+982,K0393+000-K039

Ifugao 1st DEO, Cordillera Administrative Region

2022₱65.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF NRJ - GUNAWAY - DIBIBI - DINGASAN ROAD, QUIRINO PROVINCE

Quirino DEO, Region II

2025₱56.2M
Past target date (DPWH On-Going)
No sat.

LAGAWE-BOLIWONG-ABINUAN ROAD LEADING TO INCHANG FALLS, LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2021₱33.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - MALDANUM - SAN BERNABE ROAD CONNECTING FEEDS PROCESSING (CORN/CASSAVA) AND ECHAGUE-JONES-MADDELA RD AND CORDON - AURORA-

Quirino DEO, Region II

2023₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO GANANO FALLS DIFFUN, QUIRINO

Quirino DEO, Region II

2023₱24.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO NAPIPIWONGAN, MABO AND DIBIWEN FALLS, AGLIPAY, QUIRINO

Quirino DEO, Region II

2023₱24.5M
Reported complete (DPWH)
View all 45 projects →

4. Implementation

Contract Amount

₱4,851,000.00

Progress

Reported complete (DPWH)

Start Date

February 22, 2021

Target End

May 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.