Flood Control and Drainage17OH0084No coordinates published by DPWH

CONSTRUCTION OF RETAINING WALL,CUT-CUT CREEK, PASAY CITY

CONSTRUCTION OF RETAINING WALL,CUT-CUT CREEK, PASAY CITY is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱17,458,840.81. Status: Reported complete (DPWH). Contractor on record: AARCON BUILDERS. Figures trace to dpwh.

South Manila DEO, National Capital Region

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: National Capital Region

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱2,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-17-0019343 · ₱311,300 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17OH0084 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF RETAINING WALL,CUT-CUT CREEK, PASAY CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay 816, Paco, Manila City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0019343

₱311,300.00 · FY2017

Released to Inawayan National Per High School as (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

386 projects · ₱11.2B total · 0 flags

Other projects by this contractor

DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱187.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0021 + (-158) - K0021 + 000, K0021 + (-229) - K0021 + (-158), K0021 + 000 - K0025 + 163

National Capital Region, National Capital Region

2024₱160.5M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0015 + 985 - K0016 + 087, K0016 + 303 - K0016 + 651; MC DONALD JCT-AGUINALDO H-WAY - K0015 + 274 - K0015 + 690 AND MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K

Cavite 3rd DEO, Region IV-A

2025₱140.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438

Cavite 1st DEO, Region IV-A

2025₱103.9M
Reported complete (100% progress, DPWH status On-Going)

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF BACOOR FLOOD CONTROL PROJECT INCL. A PUMPING STATION, (PACKAGE A), BACOOR CITY, CAVITE

Region IV-A, Region IV-A

2019₱103.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ASPHALT OVERLAY OF TANAY-SAMPALOC RD - K0066+100 - K0068+000, K0069+000 - K0070+443, TANAY, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱98.0M
Reported complete (DPWH)
View all 386 projects →

4. Implementation

Contract Amount

₱17,458,840.81

Progress

Reported complete (DPWH)

Start Date

June 29, 2017

Target End

January 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Not yet linked to a PSGC area.
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →