Construction of Revetment20G00098

Construction of Revetment at Sibalom Bridge (Abutment B Downstream), Pangpang, Sibalom, Antique

Construction of Revetment at Sibalom Bridge (Abutment B Downstream), Pangpang, Sibalom, Antique is a DPWH-tracked public work in ANTIQUE, Region VI. Reported contract value: ₱115,798,223.40. Status: Reported complete (DPWH). Contractor on record: IBC INTERNATIONAL BUILDERS CORP. Figures trace to sumbong.

ANTIQUE, Region VI
Region: Region VI

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱4,500

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-20-0016298 · ₱148,704,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-05-09 → 2023-11-10

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Antique

Based on the coordinates published with the DPWH record and NOAH file Antique.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱4,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay San Pedro, San Jose de Buenavista, Antique
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0016298

₱148,704,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0015364

₱43,125,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0014881

₱30,000,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-20-0016631

₱554,321.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-20-0017682

₱288,591.00 · FY2020

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱115,798,223.40

Progress

Reported complete (DPWH)

Start Date

November 23, 2020

Target End

January 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.