Roads18EI0090

REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG MOOECR - K0200+335 - K0200+570, BULALACAO, ORIENTAL; MINDORO

REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG MOOECR - K0200+335 - K0200+570, BULALACAO, ORIENTAL; MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱5,521,043.59. Status: Reported complete (DPWH). Contractor on record: RM SESCAR ENT 36556. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,521,043.59

Progress

Reported complete (DPWH)

Start Date

April 22, 2018

Target End

August 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.