Roads21IA0007

REHABILITATION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROAD - K1013+701 - K1014+397 (124.44555°, 11.5012°

REHABILITATION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROAD - K1013+701 - K1014+397 (124.44555°, 11.5012° is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱48,326,727.29. Status: Reported complete (DPWH). Contractor on record: CHUCON BUILDERS CORP FORMERLY: CHU CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Caray-caray Flood Control along Biliran Circumferential Road
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Biliran DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

103 projects · ₱3.2B total · 1 flags

4. Implementation

Contract Amount

₱48,326,727.29

Progress

Reported complete (DPWH)

Start Date

February 9, 2021

Target End

September 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.