Roads20PE0094

RECONSTRUCTION TO CONCRETE PAVEMENT, 280MM-ALONG CITY LIMIT-STO. TOMAS ROAD (S00404LZ)

RECONSTRUCTION TO CONCRETE PAVEMENT, 280MM-ALONG CITY LIMIT-STO. TOMAS ROAD (S00404LZ) is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱1,022,749.45. Status: Reported complete (DPWH). Contractor on record: HILLSTONE BUILDERS 33901. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,022,749.45

Progress

Reported complete (DPWH)

Start Date

October 23, 2020

Target End

November 26, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.