Construction of Flood Mitigation Structure23ME0024

Construction of Flood Control and Approach Protection of Masagana Bridge, Alabel, Sarangani Province

Construction of Flood Control and Approach Protection of Masagana Bridge, Alabel, Sarangani Province is a DPWH-tracked public work in ALABEL (CAPITAL) (SARANGANI), SARANGANI, Region XII. Reported contract value: ₱9,899,844.05. Status: Reported complete (DPWH). Contractor on record: KURDZ CONST. Figures trace to sumbong.

ALABEL (CAPITAL) (SARANGANI), SARANGANI, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Approach Protection of Masagana Bridge, Alabel, Sarangani Province
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Sarangani District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

17 projects · ₱201.6M total · 1 flags

4. Implementation

Contract Amount

₱9,899,844.05

Progress

Reported complete (DPWH)

Start Date

April 3, 2023

Target End

August 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.