Roads19EB0112

CLUSTER 2019LIP-14: CONC OF VARIOUS BRGY RDS: A) SITIO LIGANG PROPER LEADING TO SAN LUIS ES, MAMBURAO, OCC MINDORO B) SITIO UNO BALETE, BRGY. SAN LUIS, MAMBURAO, OCC MINDORO C) SITIO BIGOHAN, BRGY TANGKALAN, MAMBURAO, OCC MINDORO MAMBURAO , OCC MINDORO

CLUSTER 2019LIP-14: CONC OF VARIOUS BRGY RDS: A) SITIO LIGANG PROPER LEADING TO SAN LUIS ES, MAMBURAO, OCC MINDORO B) SITIO UNO BALETE, BRGY. SAN LUIS, MAMBURAO, OCC MINDORO C) SITIO BIGOHAN, BRGY TANGKALAN, MAMBURAO, OCC MINDORO MAMBURAO , OCC MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱8,459,378.55. Status: Reported complete (DPWH). Contractor on record: NEW MINDORENOS LUMBER HARDWARE AND GEN MERCHANDISE. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0000617

₱1,331,464,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

19EB0112 Construction Project

₱8,459,378.55 · NEW MINDOREÑOS LUMBER, HARDWARE AND GENERAL MERCHANDISE

Contractor

B

80 projects · ₱673.4M total · 0 flags

4. Implementation

Contract Amount

₱8,459,378.55

Progress

Reported complete (DPWH)

Start Date

October 4, 2019

Target End

February 26, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.