Bridges20MC0023

CONSTRUCTION OF PARALLEL BRIDGE - ARAKAN BRIDGE ALONG PACO - ROXAS - ARAKAN VALLEY - JCT. DAVAO - BUKIDNON ROAD, PRES. ROXAS, COTABATO

CONSTRUCTION OF PARALLEL BRIDGE - ARAKAN BRIDGE ALONG PACO - ROXAS - ARAKAN VALLEY - JCT. DAVAO - BUKIDNON ROAD, PRES. ROXAS, COTABATO is a DPWH-tracked public work in Cotabato 2nd DEO, Region XII. Reported contract value: ₱41,161,960.00. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Cotabato 2nd DEO, Region XII
Region: Region XII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱34,900 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱41,142,360 · THREE W BUILDERS INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-02-02 → 2025-11-30

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF PARALLEL BRIDGE - ARAKAN BRIDGE ALONG PACO - ROXAS - ARAKAN VALLEY - JCT. DAVAO - BUKIDNON ROAD, PRES. ROXAS, COTABATO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱34,900,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Camansi Flood Control along Libungan River, Camansi, Alamada, Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cotabato 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20MC0023

₱41,142,360.34 · THREE W BUILDERS INC

Award / contract ref: 20MC0023

Contractor

A

416 projects · ₱20.3B total · 2 flags

4. Implementation

Contract Amount

₱41,161,960.00

Progress

Reported complete (DPWH)

Start Date

February 19, 2020

Target End

November 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “CONSTRUCTION OF PARALLEL BRIDGE - ARAKAN BRIDGE ALONG PACO - ROXAS - ARAKAN VALLEY - JCT. DAVAO - BUKIDNON ROAD, PRES. ROXAS, COTABATO.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/8e7781c3-6225-42f4-9c60-2824f7f39323

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region XII (SOCCSKSARGEN)CotabatoAntipas
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.