Water Provision and Storage18NF0087

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM, LASICAM-PERRAL NHS, WILFREDO D. RAFOLS MEM. NHS, TAGANAAN NHS (ASA), MAT-I NHS, CIVIL SERVICE COMMISSION FIELD OFFICE, TIMAMANA NHS, SAPA ES, SURIGAO CITY STAND ALONE, AMOSLOG ES, PLACER CENTRAL ES, MAINIT CENT

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM, LASICAM-PERRAL NHS, WILFREDO D. RAFOLS MEM. NHS, TAGANAAN NHS (ASA), MAT-I NHS, CIVIL SERVICE COMMISSION FIELD OFFICE, TIMAMANA NHS, SAPA ES, SURIGAO CITY STAND ALONE, AMOSLOG ES, PLACER CENTRAL ES, MAINIT CENT is a DPWH-tracked public work in Surigao del Norte 2nd DEO, Region XIII. Reported contract value: ₱3,198,697.40. Status: Reported complete (DPWH). Contractor on record: C V CONST. Figures trace to dpwh.

Surigao del Norte 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Seawall, Brgy. San Jose, Del Carmen, Siargao, Surigao del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0009428

₱-50,000,000.00 · FY2018

Released to District Engineering Office (formerly Surigao del Norte 1st District Engineering Office) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,198,697.40

Progress

Reported complete (DPWH)

Start Date

August 26, 2018

Target End

November 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.