Buildings and Facilities17JA0146

CNSTRUCTION OF 3 STOREY 6 CLASSROOM SCHOOL BUILDING AT STA. MARIA CENTRAL SCHOOL, ZAMBOANGA CITY

CNSTRUCTION OF 3 STOREY 6 CLASSROOM SCHOOL BUILDING AT STA. MARIA CENTRAL SCHOOL, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱13,769,269.86. Status: Reported complete (DPWH). Contractor on record: LL CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Tumaga River Basin, Sta. Maria Section (Including Right of Way), Zamboanga City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0001276

₱47,493,500.00 · FY2017

Released to Division of Samar (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,769,269.86

Progress

Reported complete (DPWH)

Start Date

January 10, 2018

Target End

January 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.