GAA 2017 MFO-117M00009

ROAD UPGRADING (UNPAVED TO PAVED) ALONG SNA-LEBAK-KALAMANSIG ROAD, TINALON, SULTAN KUDARAT, K1864+471 TO K1866+182, (CHAINAGE 17471 TO CHAINAGE 19181)

ROAD UPGRADING (UNPAVED TO PAVED) ALONG SNA-LEBAK-KALAMANSIG ROAD, TINALON, SULTAN KUDARAT, K1864+471 TO K1866+182, (CHAINAGE 17471 TO CHAINAGE 19181) is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱144,693,406.32. Status: Reported complete (DPWH). Contractor on record: JARGON CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱144,693,406.32

Progress

Reported complete (DPWH)

Start Date

April 3, 2017

Target End

June 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.