CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES-QUEZON ECO-TOURISM RD - K0157+491-K0157+666, K0157+692 - K0157+906, K0157+692 - K0157+898 is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: UNIVERSAL DE LEON CONST AND AGGREGATES. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure, Villa Altamira, Brgy. 11, Lucena City, Quezon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Quezon 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

92 projects · ₱6.5B total · 17 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱241.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SAGPAT, KIBUNGAN, BENGUET TO SANTOL, LA UNION ROAD (PHASE II), KIBUNGAN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00379LZ) K0340+1361 - K0340+1477, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱125.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGNO RIVER MAIN STREAM (BANAO SECTION), BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00386LZ) K0316+375 - K0316+528, BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (DPWH)
View all 92 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

May 16, 2023

Target End

September 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.