Roads18FD0056

CONCRETING OF SITIO BALATAS , BRGY. BALIUAG VIEJO FMR, BRGY. BALIUAG VIEJO, MINALABAC, CAMARINES SUR(RE-BIDDING)

CONCRETING OF SITIO BALATAS , BRGY. BALIUAG VIEJO FMR, BRGY. BALIUAG VIEJO, MINALABAC, CAMARINES SUR(RE-BIDDING) is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱9,651,085.52. Status: Reported complete (DPWH). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-18-0032622 · · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱9,651,086 · 128 DRAGON CONSTRUCTION AND SUPPLIES

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-05-08 → 2025-03-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF SITIO BALATAS , BRGY. BALIUAG VIEJO FMR, BRGY. BALIUAG VIEJO, MINALABAC, CAMARINES SUR(RE-BIDDING)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation/Improvemen t of Cadlan Creek, Brgy. Cadlan, Pili, Camarines Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONSTRUCTION OF CONCRETE ROAD

₱9,651,085.52 · 128 DRAGON CONSTRUCTION AND SUPPLIES

Award / contract ref: 18FD0056

Contractor

B

208 projects · ₱3.4B total · 2 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY

Region V, Region V

2025₱96.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA

Region V, Region V

2024₱93.6M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)

Construction of Flood Control Structure along Basud River, Barangay San Jose, Basud, Camarines Norte

BASUD (CAMARINES NORTE), CAMARINES NORTE, Region V

2024₱86.8M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2020₱74.9M
Reported complete (DPWH)
View all 208 projects →

4. Implementation

Contract Amount

₱9,651,085.52

Progress

Reported complete (DPWH)

Start Date

June 22, 2018

Target End

October 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)Camarines SurMinalabacBaliuag Viejo
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.