Roads19FO0185

CONCRETING OF BRGY. BASICAO INTERIOR-BRGY. AGOL FMR, PIODURAN, ALBAY

CONCRETING OF BRGY. BASICAO INTERIOR-BRGY. AGOL FMR, PIODURAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱24,874,575.05. Status: Reported complete (DPWH). Contractor on record: TWINCARE BUILDERS INC. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0012920

₱80,500.00 · FY2019

Released to Pili National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

29 projects · ₱556.2M total · 0 flags

Other projects by this contractor

No sat.

CY 2024 BASIC EDUCATION FACILITIES FUND (BEFF) - CONSTRUCTION OF CLASSROOMS - CONSTRUCTION OF 2-STOREY 8-CLASSROOM AND 2 UNITS 4-STOREY 20-CLASSROOM SCHOOL BUILDINGS AT MARCIAL O. RAÑOLA MEMORIAL SCHOOL, GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2024₱145.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI PURPOSE TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR EDUCATION, SPORTS BUILDING

Albay 2nd DEO, Region V

2023₱70.3M
Past target date (DPWH On-Going)
No sat.

BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY LACAG - BARANGAY KIDACO RIVER, DARAGA, ALBAY

Albay 2nd DEO, Region V

2024₱47.8M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS(SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BARANGAY NAMANTAO ROAD WITH COMPLETE ROAD SAFETY FEATURES,DARAGA, ALBAY

Albay 2nd DEO, Region V

2024₱37.4M
Past target date (DPWH On-Going)
No sat.

BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY PAWA - BARANGAY BOGTONG RIVER, LEGASPI CITY

Albay 2nd DEO, Region V

2024₱28.7M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BARANGAY ROAD SITIO GUMIHAN, BRGY. MASLOG, LEGAZPI CITY, ALBAY

Albay 2nd DEO, Region V

2025₱21.9M
Past target date (DPWH On-Going)
View all 29 projects →

4. Implementation

Contract Amount

₱24,874,575.05

Progress

Reported complete (DPWH)

Start Date

December 16, 2019

Target End

December 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.