CONSTRUCTION OF BUNLO-IGULOT DIVERSION ROAD, BOCAUE, BULACAN

CONSTRUCTION OF BUNLO-IGULOT DIVERSION ROAD, BOCAUE, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱74,112,843.83. Status: Past target date (DPWH On-Going). Contractor on record: A L SALAZAR CONST INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (riprapping) Barangay Igulot, Bocaue, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱74,112,843.83

Progress

Past target date (DPWH On-Going)

Start Date

December 21, 2023

Target End

September 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.