GAA 2025 SSP25ID0046

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE FACILITIES CONSTRUCTION OF BOX CULVERT,BARANGAY HILABAGO,DAGAMI,LEYTE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE FACILITIES CONSTRUCTION OF BOX CULVERT,BARANGAY HILABAGO,DAGAMI,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱11,510,412.12. Status: Past target date (DPWH On-Going). Contractor on record: RCC BUILDERS AND ENT. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱11,650,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Protecting Public Infrastructure Facilities Construction of Box Culvert, Barangay Hilabago, Dagami, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,510,412.12

Progress

Past target date (DPWH On-Going)

Start Date

March 12, 2025

Target End

August 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.