Roads24IJ0083

OO1:PREVENTIVE MAINTENANCE - TERTIARY ROADS - CALBAYOG DIVERSION RD. K0736+306 - K0736+665.65, SAMAR

OO1:PREVENTIVE MAINTENANCE - TERTIARY ROADS - CALBAYOG DIVERSION RD. K0736+306 - K0736+665.65, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱25,097,155.80. Status: Reported complete (DPWH). Contractor on record: BCG DESIGN AND CONST. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24IJ0083 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-17 → 2025-04-26

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (preventive maintenance / overlay)

₱69,772,465 per km= 3.2x the Region VIII median (n=297)

Contract cost ₱25,097,156 ÷ 0.36 km read from the DPWH title (“K0736+306 - K0736+665.65”; K-post / station range length). National percentile: 91. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1:PREVENTIVE MAINTENANCE - TERTIARY ROADS - CALBAYOG DIVERSION RD. K0736+306 - K0736+665.65, SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Brgy Canlapwas, Pagsanghan, Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Samar 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

68 projects · ₱621.6M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0731+940, K0731+525 - K0732+087, SAMAR 1ST LD

Region VIII, Region VIII

2025₱28.9M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0715+000 - K0715+282, K0723+000 - K0723+586, K0724+579 - K0724+650

Region VIII, Region VIII

2024₱28.9M
Past target date (DPWH On-Going)
No sat.

CSSP- SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BRGY. POLANGI TO BRGY. LITERON, CALBIGA, SAMAR

Samar 2nd DEO, Region VIII

2025₱24.5M
Past target date (DPWH On-Going)
No sat.

CSSP- SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHAB. OF ROAD, BARANGAY LOKILOKON, PARANAS TO BARANGAY HINICA-AN, MOTIONG, SAMAR, STA. 0+700-STA. 1+228, PARANAS, SAMAR

Samar 2nd DEO, Region VIII

2025₱24.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPARK SAMAR MULTI-PURPOSE TRAINING CENTER), BRGY. PAYAO, CATBALOGAN CITY, SAMAR

Samar 2nd DEO, Region VIII

2023₱24.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONST. OF ROAD, BARANGAY TOMINAMOS TO BARANGAY MALIGAYA, STA. RITA, SAMAR, STA. 2+860.00-STA. 3+660

Samar 2nd DEO, Region VIII

2024₱24.1M
Reported complete (100% progress, DPWH status On-Going)
View all 68 projects →

4. Implementation

Contract Amount

₱25,097,155.80

Progress

Reported complete (DPWH)

Start Date

August 13, 2024

Target End

April 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)SamarCity of CalbayogRizal I
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.