CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), DAO CENTRAL SCHOOL, TOBIAS FORNIER, ANTIQUE

CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), DAO CENTRAL SCHOOL, TOBIAS FORNIER, ANTIQUE is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱2,961,527.86. Status: Reported complete (DPWH). Contractor on record: LASP MARKETING. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,961,527.86

Progress

Reported complete (DPWH)

Start Date

September 24, 2019

Target End

November 22, 2019

5. Audit