GAA 2017 MFO-116DJ0052

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN-CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, S02002LZ, K0153+520-K0155+225 CANDELARIA, QUEZON

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN-CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, S02002LZ, K0153+520-K0155+225 CANDELARIA, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱48,901,998.31. Status: Reported complete (DPWH). Contractor on record: MEGA M BUILDERS CORP FORMERLY: MEGA M BUILDERS. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱15,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0021010 · ₱300,000,000 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16DJ0052 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-09-25 → 2025-03-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN-CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, S02002LZ, K0153+520-K0155+225 CANDELARIA, QUEZON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Maapon River Flood Control Project, Brgys. San Isidro-Ibabang Owain, Sampaloc, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

154 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASSES/DIVERSION ROADS INCL. ROW TIAONG BY-PASS ROAD, ROAD AND BRIDGE WIDENING, QUEZON 2ND L.D., QUEZON PROVINCE

Quezon 2nd DEO, Region IV-A

2017₱144.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. ROSA RIVER (NEAR TRUSS BRIDGE), STO. DOMINGO SIDE, SANTA ROSA, LAGUNA

Laguna 2nd DEO, Region IV-A

2024₱93.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG ILANG-ILANG RIVER, BARANGAY PASONG CAMACHILE,PHASE I,

Cavite 1st DEO, Region IV-A

2024₱86.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG ILANG-ILANG RIVER, BARANGAY PASONG CAMACHILE,PHASE II,

Cavite 1st DEO, Region IV-A

2024₱85.9M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - SN PABLO-RIZAL-NAGCARLAN-LILIW RD - K0099 + 240 - K0099 + 828, K0099 + 841.80 - K0100 + 389

Laguna 3rd DEO, Region IV-A

2022₱78.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - LIPA CITY - ALAMINOS RD - K0080 + 482 - K0081 + 409, K0081 + 781 - K0082 + 282

Laguna 3rd DEO, Region IV-A

2021₱72.4M
Reported complete (DPWH)
View all 154 projects →

4. Implementation

Contract Amount

₱48,901,998.31

Progress

Reported complete (DPWH)

Start Date

February 13, 2017

Target End

January 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN-CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, S02002LZ, K0153+520-K0155+225 CANDELARIA, QUEZON.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/9780fb4b-02d0-409b-b850-478c6abf5b26

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)QuezonCandelariaMalabanban Sur
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.