Buildings and Facilities20GB0130

CONSTRUCTION OF 2 UNITS 1 STOREY TWO (2) CLASSROOM SCHOOL BUILDING AT LAWIGAN ES TOBIAS FORNIER (DAO

CONSTRUCTION OF 2 UNITS 1 STOREY TWO (2) CLASSROOM SCHOOL BUILDING AT LAWIGAN ES TOBIAS FORNIER (DAO is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱9,837,994.06. Status: Reported complete (DPWH). Contractor on record: ANJUSH BUILDERS 21491. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,837,994.06

Progress

Reported complete (DPWH)

Start Date

August 27, 2020

Target End

May 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.