Roads18PE0009

REHABILITATION OF PAVED ROAD - BENGUET-NUEVAVISCAYA ROAD, K0286+430-K0286+592, BOKOD, BENGUET, BENGUET

REHABILITATION OF PAVED ROAD - BENGUET-NUEVAVISCAYA ROAD, K0286+430-K0286+592, BOKOD, BENGUET, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,756,384.50. Status: Reported complete (DPWH). Contractor on record: RODEKOM GEN CONST AND ENT. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROX-18-0002448 · ₱14,611 · release to the district office, not itemized per project

    Possible match · score 0.73

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱4,756,385 · RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-02-02 → 2023-01-17

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF PAVED ROAD - BENGUET-NUEVAVISCAYA ROAD, K0286+430-K0286+592, BOKOD, BENGUET, BENGUET

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Adaoay, Kabayan, Benguet
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-18-0002448

₱14,611.00 · FY2018

Released to Division of Misamis Oriental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Rehab. VISCAYA ROAD, K0286+430-K0286+592, Bokod

₱4,756,384.50 · RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE

Award / contract ref: 18PE0009

Contractor

B

80 projects · ₱6.4B total · 29 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF ROAD, KAPANGAN, BENGUET - SAN GABRIEL, LA UNIONKAPANGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱197.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLI

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETSABLAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱173.6M
Reported complete (DPWH)

Construction of Flood Control Structure along Baroro River, Barangay Bacsil, Bacnotan, LaUnion

BACNOTAN (LA UNION), LA UNION, Region I

2024₱154.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱144.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 3 (LABEY-LACAMEN SECTION, BOKOD, BENGUET), BENGUET LONE DISTRICT

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.8M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱4,756,384.50

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

April 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Cordillera Administrative Region (CAR)BenguetBokodAmbuklao
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.