Roads24BH0344

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CAUAYAN CITY NORTHEAST ALTERNATE ROUTE, STA. 0+000 - STA. 0+600 AND STA. 1+100 - STA. 2+8

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CAUAYAN CITY NORTHEAST ALTERNATE ROUTE, STA. 0+000 - STA. 0+600 AND STA. 1+100 - STA. 2+8 is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱93,605,000.00. Status: Past target date (DPWH On-Going). Contractor on record: MC GEOMETRIC PROPORTIONS INC. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱93,605,000 · MC GEOMETRIC PROPORTIONS INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    0% reported · imagery 2023-03-21 → 2025-06-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (new paving / upgrading)

₱62,072,281 per km= 7.6x the Region II median (n=86)

Contract cost ₱93,605,000 ÷ 1.508 km read from the DPWH title (“STA. 0+000 - STA. 0+600; STA. 1+100 - STA. 2+8”; K-post / station range length). National percentile: 92. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CAUAYAN CITY NORTHEAST ALTERNATE ROUTE, STA. 0+000 - STA. 0+600 AND STA. 1+100 - STA. 2+8

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dammang West Flood Control Structure, Echague, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Isabela 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24BH0344

₱93,605,000.00 · MC GEOMETRIC PROPORTIONS INC

Contractor

C

48 projects · ₱2.0B total · 0 flags

4. Implementation

Contract Amount

₱93,605,000.00

Progress

Past target date (DPWH On-Going)

Start Date

April 15, 2025

Target End

April 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)IsabelaCity of CauayanCabaruan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.