Buildings and Facilities24K00534

CONSTRUCTION OF MARANTAO CONVENTION CENTER (PHASE 2), MARANTAO, LANAO DEL SUR

CONSTRUCTION OF MARANTAO CONVENTION CENTER (PHASE 2), MARANTAO, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱47,940,230.97. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MJALONTO BUILDER. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱47,940,230.97

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 7, 2025

Target End

August 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.